Project update


December 2025 – design phase initiated

The design phase for the reconstruction of Kemira’s buildings in Helsingborg has been initiated. The objective is to adapt the existing premises for the Ash2Phos process plant, enabling the recovery of phosphorus from sewage sludge ash.

The work is carried out in close collaboration with Veidekke and its wholly owned subsidiary Veitech. The design phase officially kicked off on 10 December and will continue until April 2026, defining the scope and technical solutions required for the future process plant.

“Reaching this milestone just before the holidays feels especially rewarding. We look forward to working closely with Veidekke and Veitech on this complex and important project,” says Linda Schwarz (to the left), Project Manager at EasyMining.

 

August 2025 – preparing for construction

The process plant design is in the final steps of a basic engineering. During the autumn a basic engineering design will be performed to outline the scope of the building modifications needed, including new systems related to this.

The building is in the final stages of extensive internal demolition work that is expected to last until mid-September 2025. This work includes the dismantling of all existing process equipment, installations and some building parts, with the aim of leaving a basically empty building where only the load-bearing floors, elevator and certain existing switchgears are preserved.

In parallel the project is in a set-up and preparation phase for the execution phase where we are looking to find the right partners for future detailed engineering and construction work, which includes building a project management team and all other disciplines of the project.